FRCM systems for the redevelopment of railway stations

National railway stations is a test bench extremely complex because they require daily maintenance work to ensure their efficiency. These works are also necessary when the infrastructures are very extensive and aged.

From one side, the maintenance concerns bridges, viaducts, service buildings, and small stations that line the local railway lines. On the other side, there are operations to align their safety requirements, especially anti-seismic.

The seismic improvement actions on the Naples-Formia line

The task faced according to the contract awarded by RFI is the seismic improvement of three stations placed on the Naples-Formia railway line. The operations were performed by the designer Eng. Antonio Durante and carried out by the architect Angelo Boemio from RFI.

To carry out this type of work, they have been chosen solutions for structural reinforcement based on FRCM composite materials

Which stations required interventions

The stations involved are the oldest in Naples-Formia:

  • in Frattamaggiore (NA)
  • the which one in Sant’Antimo (CE)
  • the last one in Nocera Inferiore (SA)

The three buildings, made of tufa masonry, needed actions aimed at their seismic improvement. In the case of the last one, Nocera Inferiore station, it was also necessary the strengthening of vaulted floors which showed evident signs of decay.

Reinforcement of masonry structures with FRCM systems

The improvement actions were performed using:

  • PBO-MESH 22/22 systema 44 g / m2 bidirectional net per 100 cm high in PBO fiber, equally distributed in warp and weft
  • MX-PBO Muratura, a cement-based inorganic fiber matrix. It is ideal for the optimal transfer of tensions from the structural element to the network
  • Together with the MX-PBO Joint inorganic matrix, PBO-Joint is a connection system for connecting existing masonry structures with FRCM structural reinforcement systems in PBO

 

Thanks to the good weight of the PBO mesh and the high-performance inorganic matrix, the system is suitable for applications especially on masonry for vaulting or male masonry. 

Realization of reinforcement bandages

The staple connector is made by using a bundle of parallel and continuous yarns/ strands. This bundle is collected inside a tubular elastic net made of polyester, polyamide and latex threads. The net is extensible both longitudinally and transversely and removable. 

Only after the impregnation with the appropriate MX-PBO Joint inorganic matrix, the bundle becomes rigid. When it is put inside the hole placed in the masonry structural element, increases the adhesion capacity of the FRCM reinforcement system in PBO with the existing support.

 

Solutions for Ruregold structural reinforcement

Specifically, the solutions adopted were structural reinforcement ones based on FRCM composite materials produced by Ruregold. The company is specialized in the reinforcement systems of concrete and masonry structures with the innovative Fiber Reinforced Cementitious Matrix, made of long PBO and carbon fibers. These fibers have a high tensile strength not subject to corrosion and they are drowned in a special inorganic matrix able to provide ts adherence with the support.

The Ruregold solution is able to increase the resistant capacity of structural elements and the ductility of masonry structures. It also has excellent resistance even to high temperatures and to cycles of frost and thaw.

 

SUBSCRIBE NOW
to our quarterly newsletter

to stay updated on news,
technologies and activities 

 

Source: Ingenio


Leggi anche

SIREG GEOTECH

SIREG GEOTECH è una società italiana di riferimento nel mercato globale delle infrastrutture e delle costruzioni civili, specializzata nella lavorazione di materie plastiche e composite. Produce direttamente ed esporta in 65 paesi nel mondo prodotti altamente specializzati per i settori Geotecnica e Ingegneria Civile per rinforzare e consolidare i terreni, rinforzare edifici storici e costruzioni civili e realizzarne di nuovi durevoli e sostenibili. …

Leggi tutto…

With the Decree of the President of the Board of Public Works n. 130 and n. 131 of 30 June 2021 the obligation of CVT for FRCM and CRM systems was extended until 30 June 2022. The Technical Assessment Certificate is mandatory for all manufacturers in order to be able to market their fibre-reinforced composite materials in Italy….

Leggi tutto…

In order to reduce waste and production time in the construction of large composite structures, the Dutch-based company Curve Works has developed an approach based on the assembly of composite panels. A series of double-curvature composite sandwich panels has been produced for a variety of applications using an automated adaptive mold both to thermoform 3D core kits and to infuse parts….

Leggi tutto…

Successful development of a lightweight thermoset based on renewable and regional raw materials. This article – published in the March issue of Compositi Magazine – talks about plastics for a green future. …

Leggi tutto…

University of Tennessee and Luna Innovations joined a partnership to replace a damaged decades-old concrete crossing in Morgan County (Tennessee) considered structurally deficient and outdated. A new high-tech bridge has been planned in north-central Tennessee equipped with a fiber-reinforced polymer (FRP) composite material structure….

Leggi tutto…